Ongoing Projects

SN Project Year Client Major Activities Status
1. Project Management and Implementation Support to Community Irrigation Project

[ADB Grant No.: G0219-NEP]

2012-2018 Department of Local Infrastructure Dev & Agri Roads,/ADB Project Management and Implementation Support to Community Irrigation
2. Construction Supervision, Quality Control & Contract Management of Civil Works in Main Canal of Rani Jamara Kulariya Irrigation Project 2014-2018

 

 

DoI/GoN

 

Design review; Construction supervision; Contract management
3.

Community Managed Irrigation Sector Project -Additional financing

2015-2021 DoI/ADB Project Implementation and Management Support
4. Technical Assistance for Implementation of Component -A, Irrigation and Water Resources Management Project 2016-2018 The World Bank/DOI Technical Assistance for Implementation
5. Construction Supervision, Quality Control and Contract Management of Construction Works of Dunduwa Main and Sikta Link Canal and Rehabilitation of Dunduwa Headworks (Ch. 0+000 to Ch. 23+200 of DISP) of Sikta Irrigation Project 2016-2019 DoI/GoN Construction Supervision, Quality Control and Contract Management of Construction Works
6. Establishment of “End-to-End” Flood Early Warning System in Koshi and West Rapti River Basins to Support and Strengthen Disaster Risk Management 2017-2018 Department of Hydrology and Meteorology, BRCH Project In-depth assessment of the Disaster Management Institutional Framework and establishment of people-centered functional “End-to-End” Flood Forecasting and Early Warning System
7. Detailed Feasibility Study of Nepal Gandak Irrigation System Extension Project 2017-2018 DoI/GoN Feasibility Study, Detailed Engineering Design
8. Pre-Feasibility Level Study of Sharada-Dang Valley Irrigation Project 2017-2018 DoI/GoN Pre-Feasibility Level Study
9. Feasibility Study of Dams in Dang Valley

(Contract No.: 04 /FS/Dams/MDVIP/073/74)

2017-2019 GoN Feasibility Study, Detailed Engineering Design
10. Detailed Feasibility Study of Detailed Engineering Planning and Design of Rani Jamara Kulariya System Extension Project, Patharaiya to Kandra, Kailali 2017-2019 GoN/DoI Detailed Feasibility Study and Detailed Engineering Design and Planning
11. Construction Supervision, Quality Control and Contract Management of Civil Works for Contract ID: RJKIP/Lamki Extension/ICB-04/072/73 2018-2021 DoI/GoN Construction supervision, quality control and contract management of civil works for the construction of 14.6 km long new branch canal (Lamki Extension) to irrigate the additional 6,000 ha command area.
12. Review of Design, Construction Supervision and Contract Management of East Main Canal-SIP 2018-2020 GoN/DoI Review of design, construction supervision and contract management of East Main Canal to develop irrigation infrastructure up to the farm level and provide assured year round irrigation to about 9,000 ha.
13. Detailed Survey and Engineering Design of Waste Water Management Project, Damak Waste Water Management Project, Jhapa 2018 DWSS Detailed Engineering Survey, Design and Report Preparation